Day by day
- Plan and permit – before work starts.
- Protect and open – floors covered, small openings cut at each fixture and along the route.
- Run the new lines – 1–3 days.
- Switch over and test – fixtures moved to the new lines, old lines capped, pressure test, inspection.
- Patch the walls – 1–2 days.
Thumbtack: pipe work 1–3 days depending on size, wall repair 1–2 days, whole job 3–5 days. Larger houses, slab homes (overhead re-route) and plaster walls take longer.
Will I have water?
The old system usually stays live while the new one is run; water is off mainly during the switch-over of each fixture. Ask your plumber for the shut-off schedule.
Slab leaks
HomeGuide: 1–3 days for most slab leak repairs. Fixr: trenchless repairs in a couple of hours, tunneling 4–6 hours.
See the day estimate for your house in the repipe calculator (Timeline panel).
Sources
- Thumbtack, How much does pipe installation or replacement cost? – last updated Oct 22, 2026.
- HomeGuide, Slab Leak Repair Cost – Oct 29, 2025.
- Fixr, Slab Leak Repair Cost – updated May 1, 2025.
All sources read on November 28, 2026. Cost guides are national ranges, not offers.